2021 ACCOMPLISHMENT ANNUAL REPORT

Real Property Taxation proved to ne one of the most potential and realistic sources of fund for the Local Government Unit when implemented properly and intensively, it could be fully utilized for additional income to finance its operations, projects and programs aside from the Internal Revenue Allotment(IRA) and local business taxes and fees.

To achieve the Real Property Taxation potential of the Local Government Unit, it is necessary and imperative for the LGU to be able to install and maintain a sound, affective and efficient Real Property Tax Administration and Maintenance

EXECUTIVE SUMMARY

As per records of this office, a total land area of nine hundred fourteen million eight hundred fifty five thousand six hundred eighteen (914, 855, 618) square meters real properties (land, building, machineries) declared for taxation purposes, of which five hundred ninety seven million one hundred twenty thousand five hundred fourteen (597, 120, 514) square meter falls under taxable with assessed value of three billion two hundred ten million fort nine thousand two hundred forty (3, 210, 049, 240) which computes a collectible tax amounting to sixty four million, two hundred thousand nine hundred eighty four and eighty centavos (P64, 200, 984.80)(1% basic tax & 1% SEF). The remaining total area of three hundred seventeen million seven hundred thirty five thousand one hundred four (317, 735, 104) square meters falls under exempt, with assessed value of four hundred ninety nine million three hundred ninety nine thousand four hundred ten (499, 377, 410) which utilized as Government Properties, Religious, Charitable, Educational, Pollution Control and other like road right of ways, legal easements, properties taken by creeks, watersheds and forest zones. As part of General revision of Assessment of Real Properties, the office conducted ocular inspections/field validations of declared Real Properties Unit (RPU’s) and appraisal of newly contracted buildings and machineries, including editing/updating Field Appraisal and Assessments Sheets(FAAS). based from the result of the field inspections and computerization of sketch maps.

Table 1: Accomplishment as to office PPA’s for the third quarter of the year.

Program/Activity/Project DescriptionTarget AccomplishmentRemarks
REVENUE GENERATION
Tax Information and education Campaign300No Scheduled Campaign due to COVID 19 pandemic
Printing of Field Appraisal and Assessment Sheets(FAAS), Tax Declaration, Notice of Assessment and Tax Bill in two(2) copies per RHU 237,3522, 556The target was not met due to postponement of the General Revision of Assessment of Real properties
Review and Approval of Field Appraisal and Assessments Sheets(FAAS) and Tax Declaration29,744426
Cancellation of previous Field Appraisal and Assessments Sheets(FAAS)29,594324
Book Filling and Binding of Field Appraisal and Assessments Sheets(FAAS)29,744426
Re-sectioning of PIM’s & Update & Maintenance Tax Map Control Roll(TMCR)1,462426
Distribution of Revised Tax Declaration with Notice of Assessment and Tax Bill (NATB) to the thirty (30) Barangay29,744426
Issuance of certified True Copies of Assessment Records/Documents1,0001,454
GENERAL ADMINISTRATIVE SERVICES
Preparation & Submission of Annual Investment Plan(AIP)11
Preparation & Submission of Office of Local Budget Proposal(LBP)11
Preparation & Submission of Office Local Budget Execution(LBE)11
Preparation & Submission of Monthly and Quarterly Report(BLGF Form 88-1)1616
Preparation & Submission of Office Performance Commitment & Review(OPCR) Forms11
Preparation & Submission of Individual Performance Commitment & Review(IPCR) Forms99
Preparation & Submission of 2020 Annual Accomplishment Report11
Preparation of Travel Order/Request and Leave of Absence400119
Preparation of Correspondence3030
Attendance to Conferences, Meetings, Training and Seminars2533
Conduct of Ocular Inspection for Re-assessment & Preparation of Inspection Report50147

Table 2: Present status of computerization of sketch map of the Field Appraisal & Assessment Sheets(FAAS).

No.BarangayStatus
1PoblacionCompleted
2AlloyCompleted
3AlimitCompleted
4AntutotPartially Completed
5BeletCompleted
6BinogawanCompleted
7BiyoyCompleted
8BuaPartially Completed
9CamamasiCompleted
10CapisaanCompleted
11CatarawanCompleted
12CordonCompleted
13DidipioPartially Completed
14DineCompleted
15KakidugenPartially Completed
16KongkongCompleted
17LupaCompleted
18MacalongCompleted
19MalabingCompleted
20MutaPartially Completed
21NantawacanPartially Completed
22PaoCompleted
23PapayaCompleted
24PaquetCompleted
25PudiPartially Completed
26SiguemCompleted
27TadjiCompleted
28TukodCompleted
29WangalCompleted
30WatwatCompleted